Time line for the Dome C Solar Radiation Research Project




2001 and 2002: Preparation for field campaigns, equipment and instrument acquisition.
 
January 2003: First field season. 32-meter tower erected at Dome C by Brandt and Six. Preliminary BRDF measurements made by Brandt and Six.
 
February to November 2003: Testing and modification of instruments.
 
December 2003 and January 2004: Second field season. Measurements of snow transmission, albedo and BRDF by Brandt, Grenfell, Hudson, Six, and Warren.
 
February to November 2004: Further testing and modification of instruments. Analysis of data from second field season.
 
December 2004 and January 2005: Third field season. Measurements of snow transmission, albedo and BRDF by Brandt, Grenfell, and Hudson.
 
February 2005 to present: Data analysis.